RENEWED WATER FLOW AND PRESSURE
REPAIR AND REPLACE WATER LINES WITH INSERTS
NO INVASIVE REPAIR WORK TO YOUR CONDO
NO LEAKS
| UNIT # | HW AFFECTS BATHROOM OR KITCHEN | ACCESS INTO UNITS BEGIN | ACCESS INTO UNITS COMPLETE | WATER OFF DATES | WATER ON DATES | STATUS | 5 DAY NOTICE LETTER | 2 DAY NOTICE LETTER |
|---|---|---|---|---|---|---|---|---|
| 01 | Kitchen | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
| 01 | Bathroom | Jun 29 | Jul 9 | Jun 29 | Jul 9 | Complete | N/A | N/A |
This riser was chosen to be rehabilitated using the Nu Flow Epoxy Pipe Lining Technology. To learn more about our process please click here. The lining was successful for the entire riser. This riser will be shut down once again in the near future to fix some low pressure issues. Dates and information on that will be forthcoming. |
||||||||
| UNIT # | HW AFFECTS BATHROOM OR KITCHEN | ACCESS INTO UNITS BEGIN | ACCESS INTO UNITS COMPLETE | WATER OFF DATES | WATER ON DATES | STATUS | 5 DAY NOTICE LETTER | 2 DAY NOTICE LETTER |
|---|---|---|---|---|---|---|---|---|
| 02 | Kitchen | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
This riser was epoxy lined as part of the initial project scope in 2014. All work on this riser has been completed to the satisfaction of the city, state and building. |
||||||||
| 02 | Bathroom | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
The lining was successful for the entire riser. This riser will be shut down once again in the near future to fix some low pressure issues. Dates and information on that will be forthcoming. |
||||||||
| UNIT # | HW AFFECTS BATHROOM OR KITCHEN | ACCESS INTO UNITS BEGIN | ACCESS INTO UNITS COMPLETE | WATER OFF DATES | WATER ON DATES | STATUS | 5 DAY NOTICE LETTER | 2 DAY NOTICE LETTER |
|---|---|---|---|---|---|---|---|---|
| 03 | Kitchen | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
| 03 | Bathroom | 29-Jun | 9-Jul | 29-Jun | 9-Jul | Complete | N/A | N/A |
This riser was chosen to be rehabilitated with the Nu Flow Epoxy Pipe Lining technology. For more information on the process click here. The lining was successful for the entire riser. This riser will be shut down once again in the near future to fix some low pressure issues. Dates and information on that will be forthcoming. |
||||||||
| UNIT # | HW AFFECTS BATHROOM OR KITCHEN | ACCESS INTO UNITS BEGIN | ACCESS INTO UNITS COMPLETE | WATER OFF DATES | WATER ON DATES | STATUS | 5 DAY NOTICE LETTER | 2 DAY NOTICE LETTER |
|---|---|---|---|---|---|---|---|---|
| 04 | Kitchen | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
| 04 | Bathroom | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
The lining was successful for the entire riser. This riser will be shut down once again in the near future to fix some low pressure issues. Dates and information on that will be forthcoming. |
||||||||
| UNIT # | HW AFFECTS BATHROOM OR KITCHEN | ACCESS INTO UNITS BEGIN | ACCESS INTO UNITS COMPLETE | WATER OFF DATES | WATER ON DATES | STATUS | 5 DAY NOTICE LETTER | 2 DAY NOTICE LETTER |
|---|---|---|---|---|---|---|---|---|
| 05 | Kitchen | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
The riser has been lined completely. |
||||||||
| 05 | Bathroom | 23-Jul | 6-Aug | 23-Jul | 6-Aug | Complete | N/A | N/A |
The units in this riser are complete. |
||||||||
| UNIT # | HW AFFECTS BATHROOM OR KITCHEN | ACCESS INTO UNITS BEGIN | ACCESS INTO UNITS COMPLETE | WATER OFF DATES | WATER ON DATES | STATUS | 5 DAY NOTICE LETTER | 2 DAY NOTICE LETTER |
|---|---|---|---|---|---|---|---|---|
| 06 | Bathroom | 9-Jul | 23-Jul | 9-Jul | 23-Jul | Complete | N/A | N/A |
The lining was successful for the entire riser. This riser will be shut down once again in the near future to fix some low pressure issues. Dates and information on that will be forthcoming. |
||||||||
| 06 | Kitchen | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
| UNIT # | HW AFFECTS BATHROOM OR KITCHEN | ACCESS INTO UNITS BEGIN | ACCESS INTO UNITS COMPLETE | WATER OFF DATES | WATER ON DATES | STATUS | 5 DAY NOTICE LETTER | 2 DAY NOTICE LETTER |
|---|---|---|---|---|---|---|---|---|
| 07 | Bathroom | 23-Jul | 6-Aug | 23-Jul | 6-Aug | Complete | N/A | N/A |
The units in this riser are complete. |
||||||||
| 07 | Kitchen | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
The riser has been lined completely. |
||||||||
| UNIT # | HW AFFECTS BATHROOM OR KITCHEN | ACCESS INTO UNITS BEGIN | ACCESS INTO UNITS COMPLETE | WATER OFF DATES | WATER ON DATES | STATUS | 5 DAY NOTICE LETTER | 2 DAY NOTICE LETTER |
|---|---|---|---|---|---|---|---|---|
| 08 | Bathroom | 9-Jul | 23-Jul | 9-Jul | 23-Jul | Complete | N/A | N/A |
The lining was successful for the entire riser. This riser will be shut down once again in the near future to fix some low pressure issues. Dates and information on that will be forthcoming. |
||||||||
| 08 | Kitchen | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
| UNIT # | HW AFFECTS BATHROOM OR KITCHEN | ACCESS INTO UNITS BEGIN | ACCESS INTO UNITS COMPLETE | WATER OFF DATES | WATER ON DATES | STATUS | 5 DAY NOTICE LETTER | 2 DAY NOTICE LETTER |
|---|---|---|---|---|---|---|---|---|
| 09 | Kitchen | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
| 09 | Bathroom | 6-Aug | 20-Aug | 6-Aug | 20-Aug | Complete | N/A | N/A |
Due to the inaccessibility of the pipes this riser was chosen to be rehabilitated with the Nu Flow Epoxy Pipe Lining technology. For more information on the process click here.
|
||||||||
| UNIT # | HW AFFECTS BATHROOM OR KITCHEN | ACCESS INTO UNITS BEGIN | ACCESS INTO UNITS COMPLETE | WATER OFF DATES | WATER ON DATES | STATUS | 5 DAY NOTICE LETTER | 2 DAY NOTICE LETTER |
|---|---|---|---|---|---|---|---|---|
| 10 | Kitchen | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
| 10 | Bathroom | 20-Aug | 3-Sep | 20-Aug | 3-Sep | Complete | N/A | N/A |
This riser is lined completely. |
||||||||
| UNIT # | HW AFFECTS BATHROOM OR KITCHEN | ACCESS INTO UNITS BEGIN | ACCESS INTO UNITS COMPLETE | WATER OFF DATES | WATER ON DATES | STATUS | 5 DAY NOTICE LETTER | 2 DAY NOTICE LETTER |
|---|---|---|---|---|---|---|---|---|
| 11 | Kitchen | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
This riser was accessible to be replaced, and is complete. |
||||||||
| 11 | Bathroom | 6-Aug | 20-Aug | 6-Aug | 20-Aug | Complete | N/A | N/A |
This riser was chosen to be rehabilitated with the Nu Flow Epoxy Pipe Lining technology. For more information on the process click here.
|
||||||||
| UNIT # | HW AFFECTS BATHROOM OR KITCHEN | ACCESS INTO UNITS BEGIN | ACCESS INTO UNITS COMPLETE | WATER OFF DATES | WATER ON DATES | STATUS | 5 DAY NOTICE LETTER | 2 DAY NOTICE LETTER |
|---|---|---|---|---|---|---|---|---|
| 12 | Kitchen | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
| 12 | Bathroom | 20-Aug | 3-Sep | 20-Au | 3-Sep | Complete | N/A | N/A |
This riser is lined completely |
||||||||
| UNIT # | HW AFFECTS BATHROOM OR KITCHEN | ACCESS INTO UNITS BEGIN | ACCESS INTO UNITS COMPLETE | WATER OFF DATES | WATER ON DATES | STATUS | 5 DAY NOTICE LETTER | 2 DAY NOTICE LETTER |
|---|---|---|---|---|---|---|---|---|
| 13 | Kitchen | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
| 13 | Bathroom | 3-Sep | 17-Sep | 3-Sep | 17-Sep | In Progress | N/A | N/A |
Due to the inaccessibility of the pipes this riser was chosen to be rehabilitated with the Nu Flow Epoxy Pipe Lining technology. For more information on the process click here. We will be in to repair drywall openings through this week. |
||||||||
| UNIT # | HW AFFECTS BATHROOM OR KITCHEN | ACCESS INTO UNITS BEGIN | ACCESS INTO UNITS COMPLETE | WATER OFF DATES | WATER ON DATES | STATUS | 5 DAY NOTICE LETTER | 2 DAY NOTICE LETTER |
|---|---|---|---|---|---|---|---|---|
| 14 | Kitchen | Complete | Complete | Complete | Complete | Complete | N/A | N/A |
| 14 | Bathroom | 3-Sep | 17-Sep | 3-Sep | 17-Sep | In Progress | N/A | N/A |
Due to the inaccessibility of the pipes this riser was chosen to be rehabilitated with the Nu Flow Epoxy Pipe Lining technology. For more information on the process click here. We will be in to repair drywall openings through this week. |
||||||||
From your friends at NuFlow Midwest, we thank you for your understanding and patience as we work to improve your home.
If you have any questions, please contact us... info@nuflowmidwest.com
If you're interested in learning more about this project and future projects, please email us.
At the 50% point in the project the residents were surveyed to evaluate our impact on their daily life and the quality of work being done in their unit. Out of the 196 units in this building we received 79 surveys back, or about 40%. Of those we received back, about 87% were positive.
"Everyone has been very nice to me and my dog during the construction, which is very much appreciated."
- Jenn, tenant at 1250 La Salle
"Everyone that has worked or been in my unit has been great at accommodating my cat. He was never locked up all day long which was my biggest worry."
- Cara, tenant at 1250 La Salle
"Communication about the project was good, questions answered, and thoughtfulness for pets was great!"
- Charla, tenant at 1250 La Salle
"Everyone has been very nice and frequent communication is much appreciated."
- Sara, tenant at 1250 La Salle
"Workers are extremely friendly, personable, and professional! Very nice to work with! Extremely accommodating!"
- Lauren, tenant at 1250 La Salle